The Enterprise Water Works Board is committed to meeting the water needs of all of our citizens.  Since 2000, the Board has taken large strides to improve the water quality and supply to our customers.  Everything from replacing early 1900's to early 1960's water mains to drilling 1000 gallons per minute wells and construction of a 1.5 million gallon elevated storage tank.  The Water Works Board Field Superintendent, Alan Mahan, has over 30 years of experience in the Water Works Profession.  Mr. Mahan works closely with the Mayor, who is also the Water Superintendent, and a team of experts including engineers and geologist in making critical decisions that affects the City's future water supply.


-3 F150 Trucks
$52,008


-2 F250 Trucks
$40,476


-Well #13 Strickland Road
$1,076,000
Project was completed July 2011.


-Well #15 Hwy 134
$963,000
Project was completed the Summer of 2012.


-Shellfield Road Water Tower
$2.1 million
Project was completed January 2013.  Capacity of the tower is 1.5 million gallons of water.

  


-16' Transmission Water Main
$893,000
Completed Spring of 2012.


-Water Main Replacement
$795,000
Project was completed May 2012.


-New Backhoe
$86,068